Project Description:
FITCHBURG- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 2
This project consists of resurfacing a section of Route 2 in Fitchburg. The western limit is a pavement joint, located just east of James Pond in Fitchburg (mile 94.9). The eastern limit is a pavement joint, located just west of South Street in Fitchburg (mile 97.9) on the Fitchburg/Leominster Townline. There will be no resurfacing or related work on and 50 feet from the beginning and end of the Monoosoc Bridges. The total length of this project is approximately 3.0 miles. The limits of work also include the ramps at Mt. Elam Road, Oak Hill Road and Palmer Road. The work to be done consists primarily of milling and resurfacing the existing mainline and ramps. Recessed polyurea pavement markings, preformed tape, and recessed reflectors shall be installed throughout the project. This project also consists of installing a high friction surface treatment on isolated segments. Related work includes clearing; adjusting and rebuilding drainage structures; replacing damaged frames and grates/covers within the traveled way with locking frames and grates/covers; resetting or replacing deficient granite edging, replacing deficient HMA berm; replacing existing substandard guardrail; and cleaning out drainage structures, drainage piping, and drainage outfalls.
Location:
  • City of Fitchburg
  • Construction Begins: Spring 2023
    Resident Engineer: Byron Beauregard
    Construction Bid Price: $6,255,181.53
    District: District 3

    Contracts (1) Progress
    # 121332 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 2 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/30/2023
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/09/2020
    Project Need Form PNF Approved 03/09/2020
    Project Initiation Form PIF Entered 03/09/2020
    Project Initiation Form PIF Approved 03/09/2020
    Project Initiation Form PRC Submitted 03/09/2020
    Project Review Committee PRC Approved 03/10/2020
    Project Status Advertised 02/04/2023
    Project Management
    100% Design 100% Package Received 11/16/2022
    100% Design 100% Package Comments to DE 12/05/2022
    25% Design 25% Package Received 09/12/2022
    75% Design 75% Package Received 09/12/2022
    75% Design 75% Package Comments to DE 10/19/2022
    Final Design PS&E Received 12/22/2022
    Final Design PS&E to FAPRO 01/23/2023