Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WESTHAMPTON- BRIDGE REPLACEMENT, W-27-028, PERRY HILL ROAD OVER NORTH BROOK OF MANHAN RIVER
The proposed project consists of the complete replacement of the bridge carrying Perry Hill Road over the North Branch of the Manhan River. Related work includes approach roadway modifications and drainage improvements.
Location:
  • Town of Westhampton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2025
    Project Manager: Harry Adolphe
    Estimated Total Contract Cost: $1,383,792.83
    Estimated Total Federal Participating Construction Cost: $1,505,591.72
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: PS&E Received (as of 04/10/2024 )

    Contracts (1) Progress
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTHAMPTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $778,234.40
    State Cost: $194,558.60
    Total Cost: $972,793.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2020
    Project Need Form PNF Approved 03/23/2020
    Project Initiation Form PIF Entered 03/23/2020
    Project Initiation Form PIF Approved 03/23/2020
    Project Initiation Form PRC Submitted 03/26/2020
    Project Review Committee PRC Approved 04/10/2020
    Project Management
    100% Design 100% Package Received 01/22/2024
    100% Design 100% Package Comments to DE 02/23/2024
    25% Design 25% Package Received 08/15/2022
    25% Design 25% Package Comments to DE 12/05/2022
    25% Design 25% Package Received - Resub 1 04/10/2023
    25% Design 25% Package Received - Resub 2 05/10/2023
    25% Design 25% Package Received - Resub 3 05/26/2023
    25% Design Design Public Hearing 01/31/2023
    75% Design 75% Package Received 07/24/2023
    75% Design 75% Package Comments to DE 08/25/2023
    Final Design PS&E Received 04/10/2024