Project Description:
SUTTON- SUPERSTRUCTURE REPLACEMENT, S-33-002, MANCHAUG ROAD OVER MUMFORD RIVER
Location:
  • Town of Sutton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2025/2026
    Project Manager: Jacob Tanoglu
    Estimated Total Contract Cost: $16,444,026.73
    Estimated Total Federal Participating Construction Cost: $17,280,627.72
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: 25% Package Received (as of 01/16/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: SUTTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $13,800,023, Design Status = 25%
  • Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $13,800,023.00
    State Cost: $0.00
    Total Cost: $13,800,023.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2020
    Project Need Form PNF Approved 03/23/2020
    Project Initiation Form PIF Entered 03/23/2020
    Project Initiation Form PIF Approved 03/23/2020
    Project Initiation Form PRC Submitted 03/26/2020
    Project Review Committee PRC Approved 04/10/2020
    Project Management
    25% Design 25% Package Received 01/16/2024