Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CAMBRIDGE- SUPERSTRUCTURE REPLACEMENT, C-01-031, US ROUTE 3/ROUTE 16/ROUTE 2 OVER MBTA REDLINE
The purpose of this project is limited to the bridge superstructure replacement and necessary approach work only. The sidewalk on the northbound direction (east side) is an existing shared use path and will be replaced in kind within the limits of bridge approach work. Fencing along the back of sidewalk will be removed and reset.
Location:
  • City of Cambridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $6,553,918.64
    Estimated Total Federal Participating Construction Cost: $7,433,112.94
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: Design Public Hearing (as of 02/27/2024 )

    Contracts (1) Progress
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CAMBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $6,604,208 (NHPP - Penalty)
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $5,283,366.40
    State Cost: $1,320,841.60
    Total Cost: $6,604,208.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2020
    Project Need Form PNF Approved 03/23/2020
    Project Initiation Form PIF Entered 03/23/2020
    Project Initiation Form PIF Approved 03/23/2020
    Project Initiation Form PRC Submitted 03/26/2020
    Project Review Committee PRC Approved 04/10/2020
    Project Management
    25% Design 25% Package Received 07/05/2023
    25% Design Design Public Hearing 02/27/2024
    Consultant Contract Process NTP Issued 09/13/2021