Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CAMBRIDGE- SUPERSTRUCTURE REPLACEMENT, C-01-031, US ROUTE 3/ROUTE 16/ROUTE 2 OVER MBTA REDLINE
This project includes replacement of the bridge superstructure which carries Alewife Brook Parkway, US Route 3, Route 16, and Route 2 over the MBTA Redline tunnel, increasing its design life and enhancing safety to all roadway users. The work consists of demolition of the existing superstructure in its entirety and its replacement using precast bridge units (PBUs), conducted in two stages to maintain vehicle access during construction. Sidewalks along the parkway (within the project limits) will be closed during construction and pedestrians will be detoured. The existing utilities over/attached to the bridge will be temporary relocated. Two-way traffic will be maintained over the bridge during majority of the construction, except over two inconsecutive long weekends at which time some detours will be needed. Similarly pedestrian and bicyclists access to the path directly below the bridge will be maintained, except during the same two long weekends. The proposed approach roadway work is limited in scope and is primarily to replace what are removed for/impacted by construction (e.g. sidewalk, guardrail). The area below the bridge that is primarily used by pedestrians and bicyclists is in poor conditions, thus will be resurfaced as a part of this work.
Location:
  • City of Cambridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $9,075,093.11
    Estimated Total Federal Participating Construction Cost: $9,750,770.13
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 100% Package Comments to DE (as of 01/13/2025 )

    Contracts (1) Progress
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CAMBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $5,946,490.40
    State Cost: $1,486,622.60
    Total Cost: $7,433,113.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2020
    Project Need Form PNF Approved 03/23/2020
    Project Initiation Form PIF Entered 03/23/2020
    Project Initiation Form PIF Approved 03/23/2020
    Project Initiation Form PRC Submitted 03/26/2020
    Project Review Committee PRC Approved 04/10/2020
    Project Management
    100% Design 100% Package Received 12/10/2024
    100% Design 100% Package Comments to DE 01/13/2025
    25% Design 25% Package Received 07/05/2023
    25% Design Design Public Hearing 02/27/2024
    75% Design 75% Package Received 07/02/2024
    Consultant Contract Process NTP Issued 09/13/2021