ADAMS- BRIDGE REPLACEMENT, A-04-038, QUALITY STREET OVER HOOSIC RIVER
The proposed design begins at the roadway's intersection with Pinnacle Drive. The intersection pavement will be rebuilt to match the existing conditions. The roadway pavement courses and base will be reconstructed and graded to match the proposed profile. The project also involves rebuilding an old temporary road alignment to allow residents access to the north side of South Willow Street by car or by foot during construction. The temporary road pavement will be excavated and replaced with loam and seed after completion of the project.
Location:
  • Town of Adams
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2025
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $4,096,912.11
    Estimated Total Federal Participating Construction Cost: $4,495,618.66
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: Design Public Hearing (as of 02/08/2024 )

    Contracts (2) Progress
    # 115750 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: ADAMS
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $3,740,355.20
    State Cost: $935,088.80
    Total Cost: $4,675,444.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2020
    Project Need Form PNF Approved 03/23/2020
    Project Initiation Form PIF Entered 03/23/2020
    Project Initiation Form PIF Approved 03/23/2020
    Project Initiation Form PRC Submitted 03/26/2020
    Project Review Committee PRC Approved 04/10/2020
    Project Management
    25% Design 25% Package Received 08/12/2022
    25% Design 25% Package Comments to DE 10/17/2022
    25% Design 25% Package Approved 12/27/2023
    25% Design Design Public Hearing 02/08/2024
    Consultant Contract Process NTP Issued 02/26/2021