Project Description:
HAMPDEN- BRIDGE REPLACEMENT, H-04-004, ROCKADUNDEE BRIDGE OVER SCANTIC RIVER
Location:
  • Town of Hampden
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Kristine Chestna
    Estimated Total Contract Cost: $3,695,000.00
    Estimated Total Federal Participating Construction Cost: $4,053,500.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 01/23/2023 )

    Contracts (1) Progress
    # 115752 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: HAMPDEN
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $3,914,040.00
    State Cost: $0.00
    Total Cost: $3,914,040.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/25/2020
    Project Need Form PNF Approved 03/25/2020
    Project Initiation Form PIF Entered 03/25/2020
    Project Initiation Form PIF Approved 03/25/2020
    Project Initiation Form PRC Submitted 03/26/2020
    Project Review Committee PRC Approved 04/10/2020
    Project Management
    Consultant Contract Process NTP Issued 01/23/2023