Project Description: |
DANVERS- MIDDLETON- BRIDGE REPLACEMENT, D-03-009=M-20-005, ANDOVER STREET (SR 114) OVER IPSWICH RIVER
The proposed roadway width shall include two - 12 foot travel lanes, one - 12 foot center turning lane, two - 2 foot shoulders, one - 2'-6" safety walk, and one - 5'-6" sidewalk. In addition, the designer shall investigate the inclusion of buffered bicycle accomodations.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Winter 2026/2027 |
Project Manager: | William F Brown![]() |
Estimated Total Contract Cost: | $22,635,055.55 |
Estimated Total Federal Participating Construction Cost: | $24,031,250.20 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
District: | District 4 |
Current Status: | The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 08/09/2022 ) |
|