DANVERS- MIDDLETON- BRIDGE REPLACEMENT, D-03-009=M-20-005, ANDOVER STREET (SR 114) OVER IPSWICH RIVER
The proposed roadway width shall include two - 12 foot travel lanes, one - 12 foot center turning lane, two - 2 foot shoulders, one - 2'-6" safety walk, and one - 5'-6" sidewalk. In addition, the designer shall investigate the inclusion of buffered bicycle accomodations.
Location:
  • Town of Danvers
  • Town of Middleton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2026/2027
    Project Manager: William F Brown
    Estimated Total Contract Cost: $22,635,055.55
    Estimated Total Federal Participating Construction Cost: $24,031,250.20
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 08/09/2022 )

    Contracts (1) Progress
    # 77855 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: DANVERS
    MIDDLETON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $4,562,696.80
    State Cost: $1,140,674.20
    Total Cost: $5,703,371.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/25/2020
    Project Need Form PNF Approved 03/25/2020
    Project Initiation Form PIF Entered 03/25/2020
    Project Initiation Form PIF Approved 03/25/2020
    Project Initiation Form PRC Submitted 03/26/2020
    Project Review Committee PRC Approved 04/10/2020
    Project Management
    Consultant Contract Process Scope to DE 04/20/2021
    Consultant Contract Process Scope to DE 08/09/2022
    Consultant Contract Process NTP Issued 10/06/2021
    Consultant Contract Process Workhours Approved 08/09/2022