DISTRICT 4- DISTRICT 6- ITS ROADWAY EQUIPMENT FOR HIGHWAY OPERATIONS
Location:
Construction Begins: Summer 2021
Resident Engineer: Scott Leisey
Construction Bid Price: $1,474,747.00
District: District 6

Contracts (2) Progress
# 100324 -- Design -- ITS
Work will consist of on-call technical support for evaluation, design, construction, implementation, and/or operations of ITS equipment, initiatives, and systems. Final
# 114725 -- Construction Contract
Installation of an Intelligent Transportation System (ITS) Consisting of 7 Closed Circuit Television Cameras (CCTV), 6 Traffic Counting Stations (TCS), and 2 Road Weather Info 92% Complete

Bridges

Contract Dates
Notice to Proceed: 08/16/2021
Contract Information
Project Designer: Consultant
Funding Source: NATIONAL HIGHWAY SYSTEM
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 04/07/2020
Project Need Form PNF Approved 04/07/2020
Project Initiation Form PIF Entered 04/07/2020
Project Initiation Form PIF Approved 04/07/2020
Project Initiation Form PRC Submitted 04/13/2020
Project Review Committee PRC Approved 04/13/2020
Project Status Advertised 06/05/2021
Project Management
100% Design 100% Package Received 03/08/2021
100% Design 100% Package Comments to DE 04/07/2021
25% Design 25% Package Received 01/06/2021
75% Design 75% Package Received 01/06/2021
75% Design 75% Package Comments to DE 02/09/2021
Final Design PS&E Received 05/13/2021
Final Design PS&E to FAPRO 05/21/2021