Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 3- ITS ROADWAY EQUIPMENT FOR HIGHWAY OPERATIONS
Location:
Construction Begins: Summer 2021
Resident Engineer: Adam Nabulsi
Construction Bid Price: $2,135,135.00
District: District 3

Contracts (2) Progress
# 100324 -- Design -- ITS
Work will consist of on-call technical support for evaluation, design, construction, implementation, and/or operations of ITS equipment, initiatives, and systems. Final
# 114625 -- Construction Contract
Installation of an Intelligent Transportation System (ITS) Consisting of 2 Closed Circuit Television Cameras (CCTV), 5 Variable Message Signs (VMS) and 2 Road Weather Informat Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/12/2021
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/07/2020
    Project Need Form PNF Approved 04/07/2020
    Project Initiation Form PIF Entered 04/07/2020
    Project Initiation Form PIF Approved 04/07/2020
    Project Initiation Form PRC Submitted 04/13/2020
    Project Review Committee PRC Approved 04/13/2020
    Project Status Advertised 05/22/2021
    Project Management
    100% Design 100% Package Received 02/23/2021
    100% Design 100% Package Comments to DE 03/26/2021
    25% Design 25% Package Received 12/23/2020
    75% Design 75% Package Received 12/23/2020
    75% Design 75% Package Comments to DE 01/25/2021
    Final Design PS&E Received 04/23/2021
    Final Design PS&E to FAPRO 05/07/2021