Project Description:
NEW BEDFORD- INTERSECTION IMPROVEMENTS AT MOUNT PLEASANT STREET AND NASH ROAD
Improvements are expected to include rehabilitated pavement, new traffic signals, improved sidewalks, pedestrian ramps and crosswalks. Bicycle accommodation will be incorporated as much as practicable.
Location:
  • City of New Bedford
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2027
    Project Manager: Dongke Yu
    Estimated Total Contract Cost: $3,026,001.00
    Estimated Total Federal Participating Construction Cost: $3,276,701.10
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: NEW BEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $3,538,837 - STBG d) EC Score 53 of 100; h) Project Proponent - New Bedford; i) Status Pre 25%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,831,069.60
    State Cost: $707,767.40
    Total Cost: $3,538,837.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/07/2020
    Project Need Form PNF Approved 02/04/2020
    Project Initiation Form PIF Entered 04/07/2020
    Project Initiation Form PIF Approved 04/07/2020
    Project Initiation Form PRC Submitted 04/07/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Management