Project Description: |
FALL RIVER- INTERCHANGE IMPROVEMENTS AT ROUTE 24 AND ROUTE 79
Work on this project consists of interchange improvements by reconfiguring the confluence of the merges to better separate traffic and provide a seamless flow.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Valerie E Kilduff |
Estimated Total Contract Cost: | $96,430,501.00 |
Estimated Total Federal Participating Construction Cost: | $100,002,001.05 |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|