DISTRICT 6- BOSTON INNER HARBOR STORMWATER IMPROVEMENTS
The purpose of the project is to provide water quality improvements to the Boston Inner Harbor through Stormwater Best Management Practices (BMPs). The scope of work will include, but not be limited to, the constructions of two BMPs along the Massachusetts Ave Connector and the Access Road off I-93 Frontage Road. The scope of work will also include, but not be limited to, milling and overlaying of roadway surface, drainage improvements through repair and replacement, and minimal utility relocation.
Location:
Construction Begins: Spring 2023
Resident Engineer: Ahmad Ilyas
Construction Bid Price: $1,228,433.95
District: District 6

Contracts (3) Progress
# 121697 -- Construction Contract
Boston Inner Harbor Stormwater Improvements 1% Complete
# 77887 -- Design -- Hwy Eng Open End
Master Service Agreement for statewide design and review services. Final
# 86787 -- Design -- Services
Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

Bridges

Contract Dates
Notice to Proceed: 06/09/2023
Contract Information
Project Designer: Consultant
Funding Source: FED. AID. ACCELERATED BRIDGE
See the Milestone Details tab for additional Project information
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 04/09/2020
Project Need Form PNF Approved 04/02/2020
Project Initiation Form PIF Entered 04/09/2020
Project Initiation Form PIF Approved 04/09/2020
Project Initiation Form PRC Submitted 04/10/2020
Project Review Committee PRC Approved 04/16/2020
Project Status Advertised 03/25/2023
Project Management
100% Design 100% Package Received 11/14/2022
25% Design 25% Package Received 12/21/2021
25% Design 25% Package Received 12/21/2021
75% Design 75% Package Received 12/21/2021
75% Design 75% Package Comments to DE 02/20/2022
Final Design PS&E Received 11/14/2022
Final Design PS&E Received - Resub 1 03/06/2023
Final Design PS&E Received - Resub 2 03/03/2023