QUINCY- INTERSECTION IMPROVEMENTS AT WILLARD STREET AND RICCIUTI DRIVE
The scope of work is expected to include the reconstruction of the intersection to either a signalized intersection or a roundabout alternative. The construction of a traffic signal would include all major items needed for the traffic signal system itself as well as some modifications to the geometry of the intersection including moving curb line, reconstructing sidewalk, and potentially moving drainage structures as needed from the geometric changes. The roundabout alternative would require more major changes to curb, sidewalk, and drainage structures as the geometry of the intersection would be changed entirely.
Location:
  • City of Quincy
  • Design Responsibility: Municipality
    Construction Begins: Summer 2026
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $3,176,795.24
    Estimated Total Federal Participating Construction Cost: $3,558,217.30
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 75% Package Received - Resub 1 (as of 06/12/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,696,817.70
    State Cost: $188,535.30
    Total Cost: $1,885,353.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/10/2020
    Project Need Form PNF Approved 04/09/2020
    Project Initiation Form PIF Entered 04/10/2020
    Project Initiation Form PIF Approved 04/10/2020
    Project Initiation Form PRC Submitted 04/10/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Management
    25% Design 25% Package Received 09/28/2022
    25% Design 25% Package Received - Resub 1 01/27/2023
    25% Design Design Public Hearing 08/29/2023
    75% Design 75% Package Received 12/13/2023
    75% Design 75% Package Received - Resub 1 06/12/2024