Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
QUINCY- INTERSECTION IMPROVEMENTS AT WILLARD STREET AND RICCIUTI DRIVE
The proposed project consists of the reconstruction of the intersection of Willard Street, Ricciuti Drive, and the I-93 Southbound Exit 8 Off-Ramp in Quincy, MA. The improvements proposed as part of this project will address the existing safety concerns and improve pedestrian and bicycle accommodations. The project begins on the I-93 off-ramp and extends approximately 910 feet to the existing rotary, just east of Douglas Street. Project limits also includes approximately 100 feet west on Ricciuti Drive and 800 feet north on Willard Street. Project includes signalization of the intersection of I-93 Southbound off-ramp/Willard Street and Ricciuti Drive and improvement to the lane geometry on the Willard Street approach. This project includes pavement milling and overlay, upgraded signing and striping, five-foot-wide on-street bike lanes, ADA-compliant curb ramps, and sidewalk/driveway reconstructions as needed. A Rectangular Rapid Flashing Beacon (RRFB) is also included at the northern limit of Willard Street to increase pedestrian safety.
Location:
  • City of Quincy
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Kathy Dougherty
    Estimated Total Contract Cost: $3,082,688.80
    Estimated Total Federal Participating Construction Cost: $3,414,365.71
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 100% Package Received - Resub 1 (as of 09/09/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: QUINCY
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC = $3,700,546 (HSIP). Project initially funded in FFY 2026 of the FFYs 2025–29 TIP.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,330,491.40
    State Cost: $370,054.60
    Total Cost: $3,700,546.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/10/2020
    Project Need Form PNF Approved 04/09/2020
    Project Initiation Form PIF Entered 04/10/2020
    Project Initiation Form PIF Approved 04/10/2020
    Project Initiation Form PRC Submitted 04/10/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Management
    100% Design 100% Package Received 05/14/2025
    100% Design 100% Package Comments to DE 07/11/2025
    100% Design 100% Package Received - Resub 1 09/09/2025
    25% Design 25% Package Received 09/28/2022
    25% Design 25% Package Received - Resub 1 01/27/2023
    25% Design Design Public Hearing 08/29/2023
    75% Design 75% Package Received 12/13/2023
    75% Design 75% Package Received - Resub 1 06/12/2024