Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STURBRIDGE- BRIDGE REPLACEMENT, S-30-019, CHAMPEAUX ROAD OVER LONG POND
The scope of work will consist of full replacement of the bridge that carries Champeaux Road over Long Pond in Sturbridge and any related improvements to the roadway approaches.
Location:
  • Town of Sturbridge
  • Construction Begins: Summer 2023
    Resident Engineer: David Windoloski
    Construction Bid Price: $2,363,830.00
    District: District 3

    Contracts (2) Progress
    # 122600 -- Construction Contract
    Bridge Replacement, S-30-019, Champeaux Road over Long Pond 35% Complete
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/22/2023
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/14/2020
    Project Initiation Form PIF Entered 04/14/2020
    Project Initiation Form PRC Submitted 04/14/2020
    Project Review Committee PRC Approved 04/30/2020
    Project Status Advertised 06/24/2023
    Project Management
    100% Design 100% Package Received 05/18/2022
    100% Design 100% Package Comments to DE 08/18/2022
    25% Design 25% Package Received 04/28/2021
    25% Design 25% Package Comments to DE 06/15/2021
    25% Design 25% Package Approved 06/30/2021
    25% Design Design Public Hearing 08/02/2021
    75% Design 75% Package Received 01/26/2022
    75% Design 75% Package Comments to DE 04/27/2022
    Final Design PS&E Received 03/03/2023
    Final Design PS&E to FAPRO 06/08/2023