Project Description: |
NEW BEDFORD- CORRIDOR IMPROVEMENTS ON ROUTE 18 BETWEEN ROUTE 6 AND ROUTE I-195
Work on this project includes roadway reconstruction, installation of pedestrian and bicycle accommodation, and installation of traffic signals.This project will provide multi modal improvements on Route 18 between Route 6 and I-195. It will provide connectivity between local neighborhoods and the waterfront
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Michael Trepanier |
Estimated Total Contract Cost: | $14,900,011.00 |
Estimated Total Federal Participating Construction Cost: | $14,000,008.40 |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|