DISTRICT 3- DEPLOYMENT OF TEMPORARY TRAFFIC CONTROL AT VARIOUS LOCATIONS
Work under this contract will consist of furnishing, deploying, maintaining, and removing traffic control devices on various state highways as directed by the Engineer. The work will consist of scheduled work and emergency work in support of maintenance operations.
Location:
Construction Begins: Summer 2021
Resident Engineer: John Conroy
Construction Bid Price: $305,062.45
District: District 3

Contracts (1) Progress
# 114624 -- Construction Contract
Deployment of Temporary Traffic Control at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/07/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/22/2020
    Project Initiation Form PIF Entered 05/26/2020
    Project Initiation Form PRC Submitted 05/29/2020
    Project Review Committee PRC Approved 06/02/2020
    Project Status Advertised 05/22/2021
    Project Management
    Final Design PS&E Received 04/29/2021
    Final Design PS&E to FAPRO 05/06/2021