Project Description:
NATICK- PEDESTRIAN/BIKE BRIDGE SUPERSTRUCTURE REPLACEMENT, N-03-007, SPRING STREET OVER THE MBTA
The scope of work for this project will consist of replacing the existing bridge superstructure with a Prefabricated Pedestrian-Bike Bridge at the same location.
Location:
  • Town of Natick
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2025
    Project Manager: William F Brown
    Estimated Total Contract Cost: $2,631,195.90
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: PS&E Received - Resub 2 (as of 10/09/2024 )

    Contracts (1) Progress
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2020
    Project Initiation Form PIF Entered 05/29/2020
    Project Initiation Form PRC Submitted 06/02/2020
    Project Review Committee PRC Approved 06/02/2020
    Project Management
    100% Design 100% Package Received 06/24/2024
    100% Design 100% Package Comments to DE 07/25/2024
    25% Design 25% Package Received 10/05/2023
    25% Design 25% Package Comments to DE 11/06/2023
    25% Design Design Public Hearing 03/14/2024
    75% Design 75% Package Received 03/29/2024
    75% Design 75% Package Received 03/29/2024
    Final Design PS&E Received 06/24/2024
    Final Design PS&E Received - Resub 2 10/09/2024
    Consultant Contract Process Scope to DE 05/10/2022
    Consultant Contract Process NTP Issued 10/21/2022