Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY STRUCTURAL & SUBSTRUCTURE REPAIRS AT VARIOUS LOCATIONS
This project will consist of supplying materials & labor to address structural and sub-structural problems at various bridges.
Location:
Construction Begins: Spring 2021
Resident Engineer: John Wagner
Construction Bid Price: $2,816,329.75
District: District 6

Contracts (1) Progress
# 114154 -- Construction Contract
Scheduled and Emergency Bridge Structural and Substructure Repairs at Various Locations 63% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/14/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/19/2020
    Project Initiation Form PIF Entered 06/19/2020
    Project Initiation Form PRC Submitted 06/19/2020
    Project Review Committee PRC Approved 06/24/2020
    Project Status Advertised 03/13/2021
    Project Management
    100% Design 100% Package Received 10/15/2020
    100% Design 100% Package Comments to DE 12/07/2020
    Final Design PS&E Received 12/21/2020
    Final Design PS&E Received - Resub 1 12/14/2021
    Final Design PS&E Received - Resub 2 02/06/2021