Project Description:
LYNN- NAHANT- NORTHERN STRAND EXTENSION
The proposed project improvements include eliminating a travel lane and constructing a 10-ft wide two-way separated bike lane with a 3-ft wide curbed median providing the separation. Existing sidewalks and street parking will be retained along the majority of the corridor with the exception of a few off-road connections in the form of a 10-ft wide shared-use path to complete the 1.9-miles. In addition to minor intersection improvements, some signal upgrades and timings are also proposed, along with pavement markings, signage, landscaping and ADA improvements along the corridor. There are a total of 17 at-grade roadway crossings between the two project termini. Crossings of the bicycle trail present both operational and safety considerations for motorists and trail users. The crossing locations are as follows; in Lynn, Western Avenue, South Street, Elm Street, Market Square, Commercial Street, South Common Street, Huss Court, Shepard Street, Blossom Street, Pleasant Street, Market Street / North Common Street / Central Avenue (City Hall Square), Tremont Street, State Street, Broad Street, Lynnway (Carroll Parkway), in Nahant, Nahant Road.
Location:
  • City of Lynn
  • Town of Nahant
  • Design Responsibility: Other
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2023
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Federal Participating Construction Cost: $10,939,360.17
    Funding Provision: This project is planned to be funded through the 2023 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: PS&E Received (as of 05/22/2023 )

    Contracts (1) Progress
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2023
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: LYNN
    NAHANT
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $7,491,000.00
    State Cost: $1,872,750.00
    Total Cost: $9,363,750.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/13/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 08/13/2020
    Project Initiation Form PIF Approved 08/13/2020
    Project Initiation Form PRC Submitted 08/13/2020
    Project Review Committee PRC Approved 09/24/2020
    Project Management
    100% Design 100% Package Received 12/23/2022
    100% Design 100% Package Comments to DE 01/25/2023
    25% Design 25% Package Received 07/02/2020
    25% Design 25% Package Approved 09/14/2021
    25% Design Design Public Hearing 11/17/2021
    75% Design 75% Package Received 04/20/2022
    75% Design 75% Package Comments to DE 06/30/2022
    Final Design PS&E Received 05/22/2023