Project Description:
LAWRENCE- INTERSECTION RECONSTRUCTION AT MARSTON STREET & EAST HAVERHILL STREET
The primary elements of the project include upgrading pedestrian accommodations at the intersection, realigning the intersection to reduce open pavement, installing ADA/AAB compliant pedestrian facilities and curb ramps, implementing access management measures for adjacent commercial driveways and resurfacing the pavement within the project limits. The project will improve the vehicular sight lines at the intersection and promote visibility of pedestrians.
Location:
  • City of Lawrence
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2024
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $1,881,274.13
    Estimated Total Federal Participating Construction Cost: $2,182,070.00
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: PS&E Received - Resub 2 (as of 11/27/2023 )

    Contracts (1) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,391,385.60
    State Cost: $347,846.40
    Total Cost: $1,739,232.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/25/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 08/25/2020
    Project Initiation Form PIF Approved 08/24/2020
    Project Initiation Form PRC Submitted 08/25/2020
    Project Review Committee PRC Approved 09/24/2020
    Project Management
    100% Design 100% Package Received 10/29/2021
    100% Design 100% Package Comments to DE 11/29/2021
    25% Design 25% Package Received 03/02/2021
    25% Design 25% Package Comments to DE 06/02/2021
    25% Design Design Public Hearing 09/27/2021
    75% Design 75% Package Received 10/29/2021
    75% Design 75% Package Comments to DE 11/29/2021
    Final Design PS&E Received 01/14/2022
    Final Design PS&E Received - Resub 1 02/15/2022
    Final Design PS&E Received - Resub 2 11/27/2023