Project Description:
LAWRENCE- INTERSECTION RECONSTRUCTION AT MARSTON STREET & EAST HAVERHILL STREET
The primary elements of the project include upgrading pedestrian accommodations at the intersection, realigning the intersection to reduce open pavement, installing ADA/AAB compliant pedestrian facilities and curb ramps, implementing access management measures for adjacent commercial driveways and resurfacing the pavement within the project limits. The project will improve the vehicular sight lines at the intersection and promote visibility of pedestrians.
Location:
  • City of Lawrence
  • Construction Begins: Summer 2024
    Resident Engineer: Daniel Boland
    Construction Bid Price: $1,908,860.26
    District: District 4

    Contracts (2) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 126011 -- Construction Contract
    Intersection Reconstruction at Marston Street & East Haverhill Street 1% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/20/2024
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/25/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 08/25/2020
    Project Initiation Form PIF Approved 08/24/2020
    Project Initiation Form PRC Submitted 08/25/2020
    Project Review Committee PRC Approved 09/24/2020
    Project Status Advertised 05/11/2024
    Project Management
    100% Design 100% Package Received 10/29/2021
    100% Design 100% Package Comments to DE 11/29/2021
    25% Design 25% Package Received 03/02/2021
    25% Design 25% Package Comments to DE 06/02/2021
    25% Design Design Public Hearing 09/27/2021
    75% Design 75% Package Received 10/29/2021
    75% Design 75% Package Comments to DE 11/29/2021
    Final Design PS&E Received 01/14/2022
    Final Design PS&E Received - Resub 1 02/15/2022
    Final Design PS&E Received - Resub 2 11/27/2023