Project Description: |
LAWRENCE- INTERSECTION RECONSTRUCTION AT MARSTON STREET & EAST HAVERHILL STREET
The primary elements of the project include upgrading pedestrian accommodations at the intersection, realigning the intersection to reduce open pavement, installing ADA/AAB compliant pedestrian facilities and curb ramps, implementing access management measures for adjacent commercial driveways and resurfacing the pavement within the project limits. The project will improve the vehicular sight lines at the intersection and promote visibility of pedestrians.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Construction Begins: | Summer 2024 |
Project Manager: | Gautam Sen |
Estimated Total Contract Cost: | $1,881,274.13 |
Estimated Total Federal Participating Construction Cost: | $2,182,070.00 |
Funding Provision: | This project is planned to be funded through the 2024 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization. |
District: | District 4 |
Current Status: | PS&E Received - Resub 2 (as of 11/27/2023 ) |
|
Bridges |
|
|
|