Project Description:
LAWRENCE- ROADWAY RECONSTRUCTION ON AMESBURY STREET
The primary elements of the project include converting Amesbury Street into a two-way travel corridor, reconstructing traffic signal equipment at the existing signalized intersections along Amesbury Street to accommodate two-way vehicular travel and to provide accessible pedestrian traffic signal infrastructure, installing ADA/AAB compliant pedestrian facilities and curb ramps throughout the corridor, implementing access management measures for adjacent commercial driveways and resurfacing the pavement within the project limits. The project also includes upgrading the terminus of the Amesbury Street corridor at the intersection of Amesbury Street, Lawrence Street and Chestnut Street by constructing a four (4) legged roundabout.
Location:
  • City of Lawrence
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Autumn 2024
    Project Manager: Daniel Wilk
    Estimated Total Contract Cost: $7,640,467.25
    Estimated Total Federal Participating Construction Cost: $8,096,581.63
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Merrimack Valley Metropolitan Planning Organization.
    District: District 4
    Current Status: 100% Package Comments to DE (as of 11/02/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Merrimack Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: LAWRENCE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Funding changed from CRSSAA to STBG and decreased from $8,315,255 to $8,096,582.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $6,477,265.60
    State Cost: $1,619,316.40
    Total Cost: $8,096,582.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/25/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 08/25/2020
    Project Initiation Form PIF Approved 08/24/2020
    Project Initiation Form PRC Submitted 08/26/2020
    Project Review Committee PRC Approved 09/24/2020
    Project Management
    100% Design 100% Package Received 09/29/2023
    100% Design 100% Package Comments to DE 11/02/2023
    25% Design 25% Package Received 04/01/2021
    25% Design 25% Package Comments to DE 07/06/2021
    25% Design 25% Package Approved 09/24/2021
    25% Design Design Public Hearing 05/04/2022
    75% Design 75% Package Received 12/21/2022
    75% Design 75% Package Comments to DE 01/27/2023