Project Description:
WESTPORT- INTERSECTION IMPROVEMENTS AT ROUTE 177 AND ROBERTS ROAD/TICKLE ROAD
The proposed project will construct a roundabout to improve safety at the intersection of Route 177 at Tickle Road and Robert Street. The roundabout will have a single-lane 110-foot inscribed circle, shifted off-center within the existing intersection of American Legion Highway (Route 177)/ Robert Street/ Tickle Road. The roundabout is sized to accommodate a WB-50 design vehicle. This work will require utility pole relocations, construction of new stormwater and drainage improvements, construction of raised splitter islands, sidewalks on the south side of Route 177 and along Robert Street, curbing, berm, an 8-foot side path with a 5-foot grass buffer on the north side of Route 177 and along Tickle Road, designated crossings, signage, striping, lighting and all other incidentals completed in place and accepted by the Engineer. Roadway approaches will be reconstructed as required to match to existing grade and provide smooth transitions.
Location:
  • Town of Westport
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2027
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $4,733,061.05
    Estimated Total Federal Participating Construction Cost: $5,646,484.78
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Southeastern Massachusetts Metropolitan Planning Organization.
    District: District 5
    Current Status: PS&E Received (as of 09/22/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Southeastern Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WESTPORT
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • a) Construction; b) Total Cost = $5,319,327 STBG d) EC Score 26 of 100; h) Project Proponent - Westport; i) Status 100%
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,255,461.60
    State Cost: $1,063,865.40
    Total Cost: $5,319,327.00

    Project Task Information
    Project Status
    Project Need Form PNF Received 08/26/2022
    Project Need Form PNF Entered 09/03/2020
    Project Need Form PNF Approved 08/26/2022
    Project Initiation Form PIF Received 08/31/2022
    Project Initiation Form PIF Entered 09/03/2020
    Project Initiation Form PIF Approved 08/31/2022
    Project Initiation Form PRC Submitted 09/03/2020
    Project Review Committee PRC Approved 09/24/2020
    Project Management
    100% Design 100% Package Received 02/27/2026
    100% Design 100% Package Comments to DE 03/29/2026
    25% Design 25% Package Received 10/12/2021
    25% Design 25% Package Comments to DE 01/11/2022
    75% Design 75% Package Received 12/12/2024
    75% Design 75% Package Comments to DE 09/12/2025
    75% Design 75% Package Comments to DE 01/19/2026
    Final Design PS&E Received 09/22/2026