Project Description: |
SOMERVILLE- BRIDGE REPLACEMENT, S-17-016 (3GF), WEBSTER AVENUE OVER MBTA & BMRR
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Alwin Ramirez |
Estimated Total Contract Cost: | $12,459,728.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 4 |
Current Status: | 25% Package Received (as of 12/13/2023 ) |
|
Bridges
|
|
|
|