Project Description:
SOMERVILLE- BRIDGE REPLACEMENT, S-17-016 (3GF), WEBSTER AVENUE OVER MBTA & BMRR
This project includes the replacement of Webster Avenue Bridge No. S-17-016 (3GF) over the MBTA & BMRR, reconstruction of each roadway approach between Prospect Street and Everett Street, exclusive of the intersections. In addition to the replacement of the bridge, Newton Street will be realigned west and east of the bridge, eliminating the skewed intersection by splitting the intersection into two “tee” intersections. Newton Street (West) will intersect Webster Avenue south of the proposed bridge and accommodate two-way traffic. Newton Street (East) of Webster Avenue will intersect with Webster Avenue north of the proposed bridge and remain one-way eastbound. The work along each section of Newton Street will be less than 500 ft in length.
Location:
  • City of Somerville
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2025
    Project Manager: Alwin Ramirez
    Estimated Total Contract Cost: $14,810,505.70
    Estimated Total Federal Participating Construction Cost: $17,229,344.80
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 25% Package Received - Resub 2 (as of 08/02/2024 )

    Contracts (1) Progress
    # 77854 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: SOMERVILLE
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $10,366,493.60
    State Cost: $2,591,623.40
    Total Cost: $12,958,117.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/18/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 09/18/2020
    Project Initiation Form PIF Approved 09/18/2020
    Project Initiation Form PRC Submitted 09/18/2020
    Project Review Committee PRC Approved 09/24/2020
    Project Management
    25% Design 25% Package Received 12/13/2023
    25% Design 25% Package Received - Resub 2 08/02/2024
    Consultant Contract Process NTP Issued 04/14/2021