Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SHEFFIELD- SUPERSTRUCTURE REPLACEMENT, S-10-024, COUNTY ROAD OVER IRONWORKS BROOK
The work under this Contract consists of the superstructure replacement of the County Road over Ironwork Brook in the Town of Sheffield. It includes the demolition of the existing bridge superstructure, partial demolition of the bridge substructure, the construction of a new single span bridge superstructure and modifications to the existing abutments and wingwalls. The proposed bridge is comprised of hot mix asphalt overlay on a reinforced concrete deck with spread deck beams supported by reinforced concrete abutments. Work under this Contract also includes approach roadway work to the limits shown on the Plans including, but not limited to, roadway reconstruction, mill and overlay, profile adjustment, roadway embankment work, highway guardrail, and other safety elements as shown on the Plans. The project includes full roadway closure during construction with an approved detour plan.
Location:
  • Town of Sheffield
  • Construction Begins: Spring 2026
    Resident Engineer: Bryce Whalen
    Construction Bid Price: $1,692,715.00
    District: District 1

    Contracts (2) Progress
    # 115750 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 133627 -- Construction Contract
    Superstructure Replacement, S-10-024, County Road over Ironworks Brook 14% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 04/08/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/05/2020
    Project Initiation Form PIF Entered 10/05/2020
    Project Initiation Form PRC Submitted 10/05/2020
    Project Review Committee PRC Approved 11/03/2020
    Project Status Advertised 02/14/2026
    Project Management
    100% Design 100% Package Received 07/10/2024
    100% Design 100% Package Comments to DE 09/10/2024
    100% Design 100% Package Received - Resub 1 10/15/2024
    25% Design 25% Package Received 04/15/2022
    25% Design 25% Package Comments to DE 07/14/2022
    25% Design 25% Package Received - Resub 1 08/17/2022
    25% Design 25% Package Received - Resub 2 10/03/2022
    25% Design Design Public Hearing 05/09/2023
    75% Design 75% Package Received 12/19/2023
    Final Design PS&E Received 04/11/2025
    Final Design PS&E Received - Resub 1 09/17/2025
    Final Design PS&E Received - Resub 2 12/16/2025
    Consultant Contract Process NTP Issued 06/04/2021