Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SHEFFIELD- SUPERSTRUCTURE REPLACEMENT, S-10-024, COUNTY ROAD OVER IRONWORKS BROOK
The work under this Contract consists of the superstructure replacement of the County Road over Ironwork Brook in the Town of Sheffield. It includes the demolition of the existing bridge superstructure, partial demolition of the bridge substructure, the construction of a new single span bridge superstructure and modifications to the existing abutments and wingwalls. The proposed bridge is comprised of hot mix asphalt overlay on a reinforced concrete deck with spread deck beams supported by reinforced concrete abutments. Work under this Contract also includes approach roadway work to the limits shown on the Plans including, but not limited to, roadway reconstruction, mill and overlay, profile adjustment, roadway embankment work, highway guardrail, and other safety elements as shown on the Plans. The project includes full roadway closure during construction with an approved detour plan.
Location:
  • Town of Sheffield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2026
    Project Manager: Kristine Chestna
    Estimated Total Contract Cost: $2,390,199.90
    Estimated Total Federal Participating Construction Cost: $2,730,975.61
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: PS&E Received (as of 04/11/2025 )

    Contracts (1) Progress
    # 115750 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: SHEFFIELD
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $2,087,351.20
    State Cost: $521,837.80
    Total Cost: $2,609,189.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/05/2020
    Project Initiation Form PIF Entered 10/05/2020
    Project Initiation Form PRC Submitted 10/05/2020
    Project Review Committee PRC Approved 11/03/2020
    Project Management
    100% Design 100% Package Received 07/10/2024
    100% Design 100% Package Comments to DE 09/10/2024
    100% Design 100% Package Received - Resub 1 10/15/2024
    25% Design 25% Package Received 04/15/2022
    25% Design 25% Package Comments to DE 07/14/2022
    25% Design 25% Package Received - Resub 1 08/17/2022
    25% Design 25% Package Received - Resub 2 10/03/2022
    25% Design Design Public Hearing 05/09/2023
    75% Design 75% Package Received 12/19/2023
    Final Design PS&E Received 04/11/2025
    Consultant Contract Process NTP Issued 06/04/2021