Project Description:
SHEFFIELD- SUPERSTRUCTURE REPLACEMENT, S-10-024, COUNTY ROAD OVER IRONWORKS BROOK
The current proposal is to replace the superstructure and keep the curb-to-curb width the same as the original (2-11-11-2). Bridge rails will be standard S3-TL4 with precast highway guardrail transitions. The top portion of the abutments will be demolished to below the bottom of the bridge seat and reconstructed with reinforced concrete. Approximately 100-ft of the existing roadway approaches will be reconstructed as necessary with appropriate guardrail transitions. The residential driveway near the southeast corner of the bridge will require accommodation. The designer will investigate and document the possible use of spread deck beams with a cast-in-place concrete deck to decrease the total superstructure depth and to minimize the new reinforced concrete cap. A galvanized steel superstructure replacement alternative will also be considered. A complete bridge replacement alternative will also be investigated to allow cost and constructability comparisons to a superstructure replacement. The bridge alignment and profile will remain approximately the same while increasing the hydraulic opening under the bridge.
Location:
  • Town of Sheffield
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2026
    Project Manager: Kristine Chestna
    Estimated Total Contract Cost: $2,232,222.72
    Estimated Total Federal Participating Construction Cost: $2,508,835.59
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: 75% Package Received (as of 12/19/2023 )

    Contracts (1) Progress
    # 115750 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: SHEFFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $1,647,331.20
    State Cost: $411,832.80
    Total Cost: $2,059,164.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/05/2020
    Project Initiation Form PIF Entered 10/05/2020
    Project Initiation Form PRC Submitted 10/05/2020
    Project Review Committee PRC Approved 11/03/2020
    Project Management
    25% Design 25% Package Received 04/15/2022
    25% Design 25% Package Comments to DE 07/14/2022
    25% Design 25% Package Received - Resub 1 08/17/2022
    25% Design 25% Package Received - Resub 2 10/03/2022
    25% Design Design Public Hearing 05/09/2023
    75% Design 75% Package Received 12/19/2023
    Consultant Contract Process NTP Issued 06/04/2021