Project Description:
FRAMINGHAM- CONSTRUCTION OF OFFICE, SALT SHEDS AND PARK AND RIDE RECONSTRUCTION ON ROUTE 9
Work consists of reconstruction of Park and Ride and relocation of Route 126 Maintenance Depot to new location with associated site work and construction of salt storage sheds, office and brine tanks. Relocation of Depot needed to install stormwater controls at existing location to address flooding on Route 9.
Location:
  • Town of Framingham
  • Construction Begins: Summer 2022
    Resident Engineer: Peter Kurt
    Construction Bid Price: $6,735,747.60
    District: District 3

    Contracts (1) Progress
    # 117495 -- Construction Contract
    Construction of Office, Salt Sheds and Park and Ride Lot Reconstruction on Route 9 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/01/2022
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/26/2020
    Project Initiation Form PIF Entered 10/26/2020
    Project Initiation Form PRC Submitted 11/20/2020
    Project Review Committee PRC Approved 11/23/2020
    Project Status Advertised 03/05/2022
    Project Management
    100% Design 100% Package Received 08/12/2021
    100% Design 100% Package Comments to DE 09/03/2021
    Final Design PS&E Received 01/28/2022
    Final Design PS&E to FAPRO 02/25/2022