Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HARVARD- LITTLETON- ACTON- CONCORD- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 2
This project is to replace and update guide and traffic signs along Route 2 between the Route 110/111 interchange in Harvard and the Route 2A intersection (Concord Rotary) in Concord, including applicable signing on intersecting secondary roadways.
Location:
  • Town of Acton
  • Town of Concord
  • Town of Harvard
  • Town of Littleton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $1,815,637.00
    Estimated Total Federal Participating Construction Cost: $1,966,254.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the STATEWIDE.
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 06/13/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: ACTON
    CONCORD
    HARVARD
    LITTLETON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • increased funding via STIP Action 6
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,661,067.00
    State Cost: $184,563.00
    Total Cost: $1,845,630.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2020
    Project Initiation Form PIF Entered 11/02/2020
    Project Initiation Form PRC Submitted 11/02/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Status Advertised 06/13/2026
    Project Management
    100% Design 100% Package Received 02/11/2026
    75% Design 75% Package Received 02/11/2026
    Final Design PS&E Received 05/06/2026
    Final Design PS&E to FAPRO 05/29/2026
    Consultant Contract Process NTP Issued 09/15/2025