Project Description:
HARVARD- LITTLETON- ACTON- CONCORD- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 2
This project is to replace and update guide and traffic signs along Route 2 between the Route 110/111 interchange in Harvard and the Route 2A intersection (Concord Rotary) in Concord, including applicable signing on intersecting secondary roadways.
Location:
  • Town of Acton
  • Town of Concord
  • Town of Harvard
  • Town of Littleton
  • Construction Begins: Summer 2026
    Resident Engineer: Kwabena Kantanka
    Construction Bid Price: $1,579,762.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the STATEWIDE.
    District: District 3

    Contracts (1) Progress
    # 134796 -- Construction Contract
    Guide and Traffic Sign Replacement on a Section of Route 2

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/28/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: STATEWIDE
    Location: Municipality
    Cities: ACTON
    CONCORD
    HARVARD
    LITTLETON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • increased funding via STIP Action 6
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,661,067.00
    State Cost: $184,563.00
    Total Cost: $1,845,630.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2020
    Project Initiation Form PIF Entered 11/02/2020
    Project Initiation Form PRC Submitted 11/02/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Status Advertised 06/13/2026
    Project Management
    100% Design 100% Package Received 02/11/2026
    75% Design 75% Package Received 02/11/2026
    Final Design PS&E Received 05/06/2026
    Final Design PS&E to FAPRO 05/29/2026
    Consultant Contract Process NTP Issued 09/15/2025