Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SPRINGFIELD- CHICOPEE- AGAWAM- GUIDE AND TRAFFIC SIGN REPLACEMENT ON INTERSTATE 291 AND A SECTION OF US ROUTE 5
Location:
  • City of Agawam
  • City of Chicopee
  • City of Springfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $1,690,942.50
    Estimated Total Federal Participating Construction Cost: $1,832,470.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: PS&E Received (as of 04/10/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CHICOPEE
    SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Funding increase in FY 2026.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,695,000.60
    State Cost: $188,333.40
    Total Cost: $1,883,334.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2020
    Project Initiation Form PIF Entered 11/02/2020
    Project Initiation Form PRC Submitted 11/02/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Management
    25% Design 25% Package Received 09/30/2025
    25% Design 25% Package Received 12/05/2025
    75% Design 75% Package Received 12/05/2025
    75% Design 75% Package Comments to DE 01/29/2026
    Final Design PS&E Received 04/10/2026
    Consultant Contract Process Scope to DE 01/10/2025
    Consultant Contract Process NTP Issued 02/12/2025