Project Description:
SPRINGFIELD- CHICOPEE- AGAWAM- GUIDE AND TRAFFIC SIGN REPLACEMENT ON INTERSTATE 291 AND A SECTION OF US ROUTE 5
Location:
  • City of Agawam
  • City of Chicopee
  • City of Springfield
  • Construction Begins: Summer 2026
    Resident Engineer: Rajeev Silveri
    Construction Bid Price: $1,395,984.25
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2

    Contracts (1) Progress
    # 134547 -- Construction Contract
    Guide and Traffic Sign Replacement on Interstate 291 and a Section of US Route 5

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/11/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: CHICOPEE
    SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Funding increase in FY 2026.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,695,000.60
    State Cost: $188,333.40
    Total Cost: $1,883,334.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2020
    Project Initiation Form PIF Entered 11/02/2020
    Project Initiation Form PRC Submitted 11/02/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Status Advertised 05/23/2026
    Project Management
    25% Design 25% Package Received 09/30/2025
    25% Design 25% Package Received 12/05/2025
    75% Design 75% Package Received 12/05/2025
    75% Design 75% Package Comments to DE 01/29/2026
    Final Design PS&E Received 04/10/2026
    Final Design PS&E to FAPRO 05/11/2026
    Consultant Contract Process Scope to DE 01/10/2025
    Consultant Contract Process NTP Issued 02/12/2025