BOSTON- GUIDE AND TRAFFIC SIGN REPLACEMENT ON I-90/I-93 WITHIN CENTRAL ARTERY/TUNNEL SYSTEM
This project is for the replacement of guide and traffic signs on I-93 and I-90 (MassPike) within the Central Artery/Tunnel system, including applicable signing on intersecting secondary roadways.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $2,066,000.00
    Estimated Total Federal Participating Construction Cost: $2,244,200.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $2,100,571.20
    State Cost: $233,396.80
    Total Cost: $2,333,968.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2020
    Project Initiation Form PIF Entered 11/02/2020
    Project Initiation Form PRC Submitted 11/02/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Management