Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- PARKING LOT IMPROVEMENTS AND SOIL REMOVAL AT PARCELS 26A AND 26B
The proposed remedial approach to address Asbestos fibers in soil (AIS) will include removing approximately 14 inches of soil containing asbestos fibers from landscape areas on Parcels 26A and 26B followed by placing a geotextile fabric and restoring the areas to existing conditions. Remediation of lead contaminated soil will include excavating a hotspot as defined by the Massachusetts Contingency Plan (MCP) from a discrete area of the Parcel 26B parking lot.
Location:
  • City of Boston
  • Construction Begins: Summer 2024
    Resident Engineer: Mauricio Morales
    Construction Bid Price: $2,203,763.00
    District: District 6

    Contracts (1) Progress
    # 126634 -- Construction Contract
    Parking Lot Improvements and Soil Removal at Parcels 26A and 26B

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/29/2024
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/23/2020
    Project Need Form PNF Approved 11/23/2020
    Project Initiation Form PIF Received 11/20/2020
    Project Initiation Form PIF Entered 11/23/2020
    Project Initiation Form PIF Approved 11/23/2020
    Project Initiation Form PRC Submitted 12/03/2020
    Project Review Committee PRC Approved 12/07/2020
    Project Status Advertised 06/29/2024
    Project Management
    100% Design 100% Package Received 04/02/2024
    100% Design 100% Package Comments to DE 04/19/2024
    100% Design 100% Package Received - Resub 1 05/28/2024
    75% Design 75% Package Received 03/12/2021
    75% Design 75% Package Received - Resub 1 12/15/2023
    Final Design PS&E Received 06/14/2024
    Final Design PS&E to FAPRO 06/24/2024