SPRINGFIELD- INTERSECTION IMPROVEMENTS AT CAREW STREET AND DWIGHT STREET
The intent of this project is to update this intersection to be safer for all users. The expected scope of this project includes either constructing a roundabout or updating the signalized intersection. The existing condition includes a signalized intersection with two lanes on Carew Street for both its approaches, Dwight Street has three lanes. The southbound approach of Dwight Street is a one way with three lanes; a left turn only, a through lane, and a shared through right turn lane. The northbound approach of Dwight Street has one right turn lane and one left turn lane. Pedestrian facilities are available but are not ADA compliant within the project limits and no bicycle facilities are present. Traffic volume analyses right-of-way and environmental impacts will dictate the lane configurations. Pedestrian and bicycle facilities will be updated where feasible.
Location:
  • City of Springfield
  • Design Responsibility: Consultant
    Project Manager: Michael Trepanier
    Estimated Total Contract Cost: $7,560,100.00
    Estimated Total Federal Participating Construction Cost: $7,840,105.00
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/18/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/18/2020
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/11/2021
    Project Review Committee PRC Approved 01/28/2021