HOLYOKE- INTERSECTION IMPROVEMENTS AT BEECH STREET, RESNIC BOULEVARD, AND WEST FRANKLIN STREET
The purpose of this project is to improve safety at the intersection of Beech Street and Resnic Boulevard in Holyoke. A teardrop-shaped roundabout will be constructed for drivers to fit within the footprint of the intersection. Bicyclists and pedestrians will be accommodated with a 10' wide shared-use path around the outside of the roundabout, some of whom are expected to be students traveling to and from Holyoke High School.
Location:
  • City of Holyoke
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $6,244,138.15
    Estimated Total Federal Participating Construction Cost: $6,767,675.05
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: 25% Package Received - Resub 1 (as of 05/12/2025 )

    Contracts (4) Progress
    # 77853 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86782 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 2. Final
    # 86787 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: HOLYOKE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $5,720,120.10
    State Cost: $635,568.90
    Total Cost: $6,355,689.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/18/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/18/2020
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/11/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management
    25% Design 25% Package Received 03/04/2024
    25% Design 25% Package Comments to DE 06/04/2024
    25% Design 25% Package Received - Resub 1 10/24/2024
    25% Design 25% Package Received - Resub 1 05/12/2025
    Consultant Contract Process NTP Issued 07/13/2021