Project Description: |
STURBRIDGE- CHARLTON- INTERSECTION IMPROVEMENTS ON ROUTE 49 AT PUTNAM ROAD, WALKER POND ROAD & ROUTE 20
The project involves intersection improvements at three locations along Route 49 - Putnam Road, Walker Pond Road and Route 20. The targeted safety improvements include construction of a roundabout at Putnam Road, improved sight lines at Walker Pond Road and slip ramp modifications at Route 20.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Summer 2027 |
Project Manager: | Janhavi Limaye |
Estimated Total Contract Cost: | $8,665,280.00 |
Estimated Total Federal Participating Construction Cost: | $9,036,685.00 |
Funding Provision: | This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization. |
District: | District 3 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 01/06/2023 ) |
|
Bridges |
|
|
|