Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
STURBRIDGE- CHARLTON- INTERSECTION IMPROVEMENTS ON ROUTE 49 AT PUTNAM ROAD, WALKER POND ROAD & ROUTE 20
The project involves intersection improvements at three locations along Route 49 - Putnam Road, Walker Pond Road and Route 20. The targeted safety improvements include construction of a roundabout at Putnam Road, improved sight lines at Walker Pond Road and slip ramp modifications at Route 20.
Location:
  • Town of Charlton
  • Town of Sturbridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2027
    Project Manager: Janhavi Limaye
    Estimated Total Contract Cost: $8,665,280.00
    Estimated Total Federal Participating Construction Cost: $9,036,685.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 01/06/2023 )

    Contracts (1) Progress
    # 86790 -- Design -- Services
    AutoCAD Base Plan Surveying Services Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: CHARLTON
    STURBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $4,060,000, Design Status = Approved, YOE = 12%
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $3,654,000.00
    State Cost: $406,000.00
    Total Cost: $4,060,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/18/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/18/2020
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/06/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management
    Consultant Contract Process NTP Issued 01/06/2023