Project Description:
EAST BRIDGEWATER- INTERSECTION IMPROVEMENTS AT BEDFORD STREET (ROUTE 18), WEST STREET (ROUTE 106) AND EAST STREET
Location:
  • Town of East Bridgewater
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $3,037,500.00
    Estimated Total Federal Participating Construction Cost: $3,500,000.00
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/18/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/18/2020
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 12/29/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Management