| Project Description: |
EAST BRIDGEWATER- INTERSECTION IMPROVEMENTS AT BEDFORD STREET (ROUTE 18), WEST STREET (ROUTE 106) AND EAST STREET
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Adam W Kiel![]() |
| Estimated Total Contract Cost: | $3,037,500.00 |
| Estimated Total Federal Participating Construction Cost: | $3,500,000.00 |
| District: | District 5 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 04/04/2025 ) |
|
Bridges |
||||||
|
|
|
|||||||||||||||||||||||||||||