Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LEE- INTERSECTION IMPROVEMENTS AT PARK STREET AND MAIN STREET (ROUTE 20)
This project will convert the three-leg intersection of Main St, Park St, and West Park St in Lee to a modern roundabout. Work will include reconstructing the intersection and each of its approaches for several hundred feet. Improvements to the existing closed drainage system will be made to accommodate the new configuration. Existing sidewalks will tie into the new intersection, new crosswalks will be added, and improved bike accommodation will be implemented (perhaps in the form of a shared-use or side path).
Location:
  • Town of Lee
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2026
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $3,512,500.00
    Estimated Total Federal Participating Construction Cost: $3,880,875.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization.
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Berkshire Metropolitan Planning Organization
    Location: Municipality
    Cities: LEE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $3,477,264.00
    State Cost: $869,316.00
    Total Cost: $4,346,580.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/21/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/21/2020
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/12/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management