| Project Description: | 
 EAST BRIDGEWATER- INTERSECTION IMPROVEMENTS AT HIGHLAND STREET AND NORTH BEDFORD STREET (ROUTE 18) 
The project proposes to improve the existing signalized intersection by either constructing a roundabout or upgrading signal equipment and tightening curb radii/modifying intersection geometry to reduce speeds and promote safety. The feasibility of constructing multi-use paths along each leg of the intersection will be explored to accommodate bicyclists and pedestrians, subject to right-of-way, environmental, utility, grading, and constructability constraints. 
 | 
| Location: | 
 | 
| Design Responsibility: | Consultant | 
| Right of Way Responsibility: | MassDOT | 
| Construction Begins: | Summer 2029 | 
| Project Manager: | Alexis  Karagounis![]()  | 
| Estimated Total Contract Cost: | $3,037,500.00 | 
| Estimated Total Federal Participating Construction Cost: | $3,500,000.00 | 
| Funding Provision: | This project is planned to be funded through the 2029 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization. | 
| District: | District 5 | 
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 07/23/2024 ) | 
  | 
Bridges | 
||||||
  | 
  | 
|||||||||||||||||||||||||||||||||||||||||
 
 
  | 
|||||||||||||||||||||||||||||