Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
EAST BRIDGEWATER- INTERSECTION IMPROVEMENTS AT HIGHLAND STREET AND NORTH BEDFORD STREET (ROUTE 18)
The project proposes to improve the existing signalized intersection by either constructing a roundabout or upgrading signal equipment and tightening curb radii/modifying intersection geometry to reduce speeds and promote safety. The feasibility of constructing multi-use paths along each leg of the intersection will be explored to accommodate bicyclists and pedestrians, subject to right-of-way, environmental, utility, grading, and constructability constraints.
Location:
  • Town of East Bridgewater
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2029
    Project Manager: Aidee Cira
    Estimated Total Contract Cost: $3,037,500.00
    Estimated Total Federal Participating Construction Cost: $3,500,000.00
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/22/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/22/2020
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 12/29/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Management