Project Description:
STOUGHTON- INTERSECTION IMPROVEMENTS AT CANTON STREET (ROUTE 27), SCHOOL STREET, SUMMER STREET AND CUSHING STREET
Location:
  • Town of Stoughton
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Aidee Cira
    Estimated Total Contract Cost: $3,704,125.70
    Estimated Total Federal Participating Construction Cost: $5,790,551.65
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Received (as of 10/01/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: STOUGHTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Total cost $4,985,836; NOT AC; YOE 2028, TEC Score: 74; Funding Source: HSIP; Pre-25%
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,846,232.70
    State Cost: $538,470.30
    Total Cost: $5,384,703.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/22/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/22/2020
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 12/29/2020
    Project Review Committee PRC Approved 12/14/2023
    Project Management
    25% Design 25% Package Received 10/08/2024
    25% Design 25% Package Comments to DE 12/12/2024
    25% Design 25% Package Approved 04/08/2025
    25% Design Design Public Hearing 06/03/2025
    75% Design 75% Package Received 10/01/2025