Project Description:
MEDFORD- SHARED USE PATH CONNECTION AT THE ROUTE 28/WELLINGTON UNDERPASS
The scope of the proposed project is to construct a multiuse boardwalk under the Route 28 bridge. The bridge is owned by MassDOT and the land the boardwalk will connect to is owned by MassDOT and DCR. A multiuse path in this location would close the gap in the area's multimodal network and connect to shared paths on either side.
Location:
  • City of Medford
  • Construction Begins: Spring 2026
    Resident Engineer: Christopher DeCaro
    Construction Bid Price: $6,881,625.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4

    Contracts (1) Progress
    # 133790 -- Construction Contract
    Shared Use Path Connection at the Route 28/Wellington Underpass

    Bridges

    Contract Dates
    Notice to Proceed: 05/13/2026
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC = $5,488,945 (CMAQ). Project initially funded in FFY 2024 of FFYs 2023–27 TIP, shifted to regional target program in FFYs 2025–29 TIP for FFY 2025.
  • increased from $5,488,945 per STSIP Action 1
  • Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $5,999,238.40
    State Cost: $1,499,809.60
    Total Cost: $7,499,048.00

    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • moved $537,326to HPP per STIP Action 1
  • Category FA - High Priority Projects (HPP)
    Federal Cost: $429,860.80
    State Cost: $107,465.20
    Total Cost: $537,326.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/23/2020
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 12/23/2020
    Project Initiation Form PIF Approved 12/23/2020
    Project Initiation Form PRC Submitted 12/23/2020
    Project Review Committee PRC Approved 01/28/2021
    Project Status Advertised 03/07/2026
    Project Management
    100% Design 100% Package Received 10/31/2024
    100% Design 100% Package Comments to DE 12/02/2023
    25% Design 25% Package Received 03/10/2022
    25% Design 25% Package Comments to DE 06/23/2022
    25% Design 25% Package Received - Resub 1 08/08/2022
    25% Design Design Public Hearing 12/08/2022
    25% Design Design Public Hearing 12/08/2022
    75% Design 75% Package Received 03/05/2024
    75% Design 75% Package Comments to DE 05/06/2024
    Final Design PS&E Received 05/28/2025
    Final Design PS&E to FAPRO 02/20/2026
    Final Design PS&E Received - Resub 1 08/06/2025
    Final Design PS&E Received - Resub 2 09/23/2025
    Final Design PS&E Received - Resub 3 12/29/2025