Project Description:
HARWICH- SIDEWALK INSTALLATION ON ROUTE 28 FROM BANK STREET TO SAQUATUCKET HARBOR
The work will include the construction of a sidewalk with associated curb ramps and crosswalks along the south side of Route 28 (Main Street) from Bank Street to the Saquatucket Harbor parking lot. A pedestrian bridge will be installed to span over an existing culvert near Wychmere Harbor Drive.
Location:
  • Town of Harwich
  • Design Responsibility: Municipality
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Thomas H Currier
    Estimated Total Contract Cost: $2,162,239.16
    Estimated Total Federal Participating Construction Cost: $2,846,756.70
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5
    Current Status: 75% Package Comments to DE (as of 06/02/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: HARWICH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • CMAQ approved; TFPC - $2,561,843
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $2,049,474.40
    State Cost: $512,368.60
    Total Cost: $2,561,843.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/05/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 01/05/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/07/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management
    25% Design 25% Package Received 04/01/2022
    25% Design Design Public Hearing 01/17/2023
    75% Design 75% Package Received 04/19/2023
    75% Design 75% Package Comments to DE 06/02/2023