Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
OXFORD- ROADWAY REHABILITATION ON ROUTE 12 (MAIN STREET)
The Oxford Town Center project will implement complete streets improvements along the Main Street (Route 12) corridor to provide multimodal and accessible accommodations for all roadway users include new bike accommodations installation of ADA/AAB compliant pedestrian facilities and construction of curb ramps throughout the corridor. The project includes safety and operational improvements at the intersection of Main Street/Charlton Street/Sutton Avenue by providing modern traffic signal equipment implementing geometric improvements and resurfacing pavement.
Location:
  • Town of Oxford
  • Design Responsibility: Municipality
    Construction Begins: Spring 2028
    Project Manager: Muazzez G Reardon
    Estimated Total Contract Cost: $8,235,000.00
    Estimated Total Federal Participating Construction Cost: $8,540,000.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: OXFORD
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $9,564,800, Design Status = Approved, YOE = 12%, PM Score = 15 out of 27
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $7,651,840.00
    State Cost: $1,912,960.00
    Total Cost: $9,564,800.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 01/08/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/12/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management