Project Description:
SOMERSET- SWANSEA- PAVEMENT PRESERVATION & RELATED WORK ON I-195
Location:
  • Town of Somerset
  • Town of Swansea
  • Construction Begins: Spring 2025
    Resident Engineer: Nelson Borges
    Construction Bid Price: $15,942,343.00
    District: District 5
    Current Status: Granite edging along on / off ramps is being removed and reset. Guardrail along mainline corridor is being replaced. Normal work hours are Monday through Friday, 7:00 to 3:30 PM. Scheduled work hours are Sunday evening through Friday morning, 8:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 10/14/2025)

    Contracts (1) Progress
    # 129599 -- Construction Contract
    Pavement Preservation & Related Work on I-195 7% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 06/04/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Granite edging along on / off ramps is being removed and reset. Guardrail along mainline corridor is being replaced. Normal work hours are Monday through Friday, 7:00 to 3:30 PM. Scheduled work hours are Sunday evening through Friday morning, 8:00 PM to 5:00 AM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 01/08/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/08/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Status Advertised 03/01/2025
    Project Management
    100% Design 100% Package Received 03/15/2023
    25% Design 25% Package Received 01/05/2022
    75% Design 75% Package Received 01/05/2022
    75% Design 75% Package Comments to DE 04/19/2022
    Final Design PS&E Received 03/15/2023
    Final Design PS&E Received - Resub 1 08/12/2024