Project Description:
NEW BEDFORD- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 140
Location:
  • City of New Bedford
  • Construction Begins: Winter 2023/2024
    Resident Engineer: Nelson Borges
    Construction Bid Price: $11,228,482.00
    District: District 5
    Current Status: Currently performing Guardrail Replacement along project corridor during day hours 7:00 to 3:00. Switching to night work 4/27/25, 9:00 PM to 5:00 AM. Scheduled work hours are Sunday through Thursday 8:00 PM to 5:30 AM. Expect periodic lane closures and restrictions. (as of 04/09/2025)

    Contracts (1) Progress
    # 124528 -- Construction Contract
    Pavement Preservation and Related Work on Route 140 40% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 01/16/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Currently performing Guardrail Replacement along project corridor during day hours 7:00 to 3:00. Switching to night work 4/27/25, 9:00 PM to 5:00 AM. Scheduled work hours are Sunday through Thursday 8:00 PM to 5:30 AM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 01/08/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/08/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Status Advertised 11/04/2023
    Project Management
    100% Design 100% Package Received 08/02/2022
    25% Design 25% Package Received 01/05/2022
    75% Design 75% Package Received 01/05/2022
    75% Design 75% Package Comments to DE 04/13/2022
    Final Design PS&E Received 08/02/2022
    Final Design PS&E Received - Resub 1 05/08/2023