NEWTON- HORACE MANN ELEMENTARY SCHOOL IMPROVEMENTS (SRTS)
The project will upgrade the intersections of Crafts/Albemarle and Albemarle/North with an eye towards improving bicycle and pedestrian accommodations to and from the Horace Mann Elementary School, F.A. Day Middle School and the Newton Early Childhood Program. The project as proposed includes installing a fully actuated traffic signal at the Crafts/Albemarle and a rapid flashing beacon crosswalk system at the Albemarle/North.
Location:
  • City of Newton
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2025
    Project Manager: Stephanie Upson
    Estimated Total Contract Cost: $724,500.00
    Estimated Total Federal Participating Construction Cost: $828,112.50
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (2) Progress
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86787 -- Design -- Services
    Work will consist of performing the collection of electronic field survey data and the completion of AutoCAD Base Plans for highway and bridge projects throughout District 4. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NEWTON
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $861,237 (TAP)
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $688,989.60
    State Cost: $172,247.40
    Total Cost: $861,237.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/08/2021
    Project Need Form PNF Approved 01/06/2021
    Project Initiation Form PIF Entered 01/08/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/11/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management