Project Description:
MEDFORD- MILTON FULLER ROBERTS ELEMENTARY SCHOOL (SRTS)
Pedestrian improvements at three key intersections for students approaching the Roberts School. Improvements would include: 1) A full pedestrian signal, curb extensions and improved lighting at the intersection of Fellsway with Paris Street and Fern Road and sidewalk improvements from this intersection to the school along Park Street; 2) Pedestrian realignment, curb bumpouts and pedestrian Rectangular Rapid Flashing Beacons (RRFBs) at the intersection of Salem Street and Hadley Place; and 3) Pedestrian RRFBs, curb extensions and improved lighting at the intersection of Fellsway and Grant Avenue or Sheridan Avenue.
Location:
  • City of Medford
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2026
    Project Manager: Filbert Yee
    Estimated Total Contract Cost: $850,392.00
    Estimated Total Federal Participating Construction Cost: $981,235.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 09/22/2023 )

    Contracts (1) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: MEDFORD
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $816,387.20
    State Cost: $204,096.80
    Total Cost: $1,020,484.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/11/2021
    Project Need Form PNF Approved 01/01/1900
    Project Initiation Form PIF Entered 01/11/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 01/11/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management
    Consultant Contract Process NTP Issued 09/22/2023