Project Description:
DUXBURY- BRIDGE REPLACEMENT, D-14-003 (438), POWDER POINT AVENUE OVER DUXBURY BAY
The proposed project will consist of a complete replacement of the existing bridge, that carries Powder Point Avenue over Duxbury Bay in Duxbury.
Location:
  • Town of Duxbury
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Bryan J Cordeiro
    Estimated Total Contract Cost: $83,052,000.00
    Estimated Total Federal Participating Construction Cost: $86,128,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Old Colony Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (1) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: DUXBURY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG) - Off System Bridge
    Federal Cost: $37,942,450.40
    State Cost: $9,485,612.60
    Total Cost: $47,428,063.00

    Planned Federal FY: 2027
    Responsible MPO: Old Colony Metropolitan Planning Organization
    Location: Municipality
    Cities: DUXBURY
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Bridge Formula Program - Local Off System Bridge
    Federal Cost: $31,139,937.00
    State Cost: $0.00
    Total Cost: $31,139,937.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/25/2021
    Project Initiation Form PIF Entered 01/25/2021
    Project Initiation Form PRC Submitted 01/25/2021
    Project Review Committee PRC Approved 01/28/2021
    Project Management