Project Description:
WORCESTER- INTERSECTION IMPROVEMENTS AND RESURFACING ON CHANDLER STREET, FROM QUEEN STREET TO PARK AVENUE
The project extends along Chandler Street, from 200 feet west of Queen Street to 200 feet west of Park Avenue, a distance of 3.7 miles. The proposed improvements include roadway resurfacing, traffic signal reconstruction, and bicycle and pedestrian improvements. Related work involves an adaptive signal control system, sidewalk reconstruction, granite curbing, improved signage and pavement markings.
Location:
  • City of Worcester
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: Adam W Kiel
    Estimated Total Contract Cost: $3,915,000.00
    Estimated Total Federal Participating Construction Cost: $4,205,000.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Central Massachusetts Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Central Massachusetts Metropolitan Planning Organization
    Location: Municipality
    Cities: WORCESTER
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Construction, Total Project Cost = $4,709,600, Design Status = Approved, YOE = 12%, PM Score = 17 out of 27
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,238,640.00
    State Cost: $470,960.00
    Total Cost: $4,709,600.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/11/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/11/2021
    Project Initiation Form PIF Approved 02/11/2021
    Project Initiation Form PRC Submitted 02/24/2021
    Project Review Committee PRC Approved 02/24/2021
    Project Management