WORTHINGTON- RESURFACING AND RELATED WORK ON ROUTE 112
Project includes resurfacing and related work on Route 112 in Worthington from approximate mile marker 8.5 (Huntington town line) to mile marker 14.4 (Route 143 @ Worthington Corners). Project scope is typical of standard National Highway System resurfacing, with the primary project need being pavement preservation.
Location:
  • Town of Worthington
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Daniel Wilk
    Estimated Total Contract Cost: $6,797,972.48
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: PS&E Received (as of 08/28/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/22/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/22/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 02/22/2021
    Project Review Committee PRC Approved 03/03/2021
    Project Management
    100% Design 100% Package Received 06/06/2024
    100% Design 100% Package Comments to DE 07/11/2024
    25% Design 25% Package Received 03/08/2024
    75% Design 75% Package Received 03/08/2024
    75% Design 75% Package Comments to DE 04/09/2024
    Final Design PS&E Received 08/28/2024