Project Description: |
TRURO- WELLFLEET- RESURFACING AND RELATED WORK ON ROUTE 6
Work on this project will include resurfacing Route 6. No significant expansion of bike/ped facilities. Segment can be advanced as a pavement preservation focused endeavor due to limited priority or demand for expansion of existing multimodal facilities. If needed, accessible ped ramp should be provided at existing sidewalk infrastructure. Existing sidewalks should be repaired if necessary and cross-sectional distribution should be investigated through pavement marking changes for crosswalks, bicycle accommodations.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Autumn 2026 |
Project Manager: | Gregory Mischel |
Estimated Total Contract Cost: | $17,200,464.75 |
Estimated Total Federal Participating Construction Cost: | $18,021,646.30 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization. |
District: | District 5 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|