PROVINCETOWN- TRURO- WELLFLEET- RESURFACING AND RELATED WORK ON ROUTE 6
Work on this project will include resurfacing Route 6. No significant expansion of bike/ped facilities. Segment can be advanced as a pavement preservation focused endeavor due to limited priority or demand for expansion of existing multimodal facilities. If needed, accessible ped ramp should be provided at existing sidewalk infrastructure. Existing sidewalks should be repaired if necessary and cross-sectional distribution should be investigated through pavement marking changes for crosswalks, bicycle accommodations.
Location:
  • Town of Provincetown
  • Town of Truro
  • Town of Wellfleet
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2026
    Project Manager: Gregory Mischel
    Estimated Total Contract Cost: $17,200,464.75
    Estimated Total Federal Participating Construction Cost: $18,021,646.30
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Cape Cod Metropolitan Planning Organization.
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Cape Cod Metropolitan Planning Organization
    Location: Municipality
    Cities: PROVINCETOWN
    TRURO
    WELLFLEET
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • TFPC - $14,665,155; GHG analysis to be completed when all required inputs are available
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $11,732,124.00
    State Cost: $2,933,031.00
    Total Cost: $14,665,155.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/22/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/22/2021
    Project Initiation Form PIF Approved 02/22/2021
    Project Initiation Form PRC Submitted 02/22/2021
    Project Review Committee PRC Approved 03/03/2021
    Project Management