Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WOBURN- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95
Location:
  • City of Woburn
  • Construction Begins: Summer 2024
    Resident Engineer: John Mitchell
    Construction Bid Price: $12,477,521.65
    District: District 4

    Contracts (1) Progress
    # 125647 -- Construction Contract
    Interstate Pavement Preservation and Related Work on I-95

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/01/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/23/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/23/2021
    Project Initiation Form PIF Approved 02/23/2021
    Project Initiation Form PRC Submitted 02/23/2021
    Project Review Committee PRC Approved 03/03/2021
    Project Status Advertised 03/30/2024
    Project Management
    100% Design 100% Package Received 02/22/2024
    25% Design 25% Package Received 11/07/2023
    75% Design 75% Package Received 11/07/2023
    75% Design 75% Package Comments to DE 12/08/2023
    Final Design PS&E Received 02/22/2024
    Final Design PS&E to FAPRO 03/18/2024