Project Description:
BROOKLINE- NEWTON- RESURFACING AND RELATED WORK ON ROUTE 9
Location:
  • Town of Brookline
  • City of Newton
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2025
    Project Manager: Eric I Nova
    Estimated Total Contract Cost: $9,373,718.50
    Estimated Total Federal Participating Construction Cost: $9,547,287.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: 100% Package Received (as of 10/09/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BROOKLINE
    NEWTON
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $6,941,584.00
    State Cost: $1,735,396.00
    Total Cost: $8,676,980.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/23/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/23/2021
    Project Initiation Form PIF Approved 01/01/1900
    Project Initiation Form PRC Submitted 03/01/2021
    Project Review Committee PRC Approved 03/03/2021
    Project Management
    100% Design 100% Package Received 10/09/2024
    25% Design 25% Package Received 07/29/2024
    75% Design 75% Package Received 07/29/2024
    75% Design 75% Package Comments to DE 08/29/2024
    Final Design PS&E Received 10/09/2024