Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
GLOUCESTER- RESURFACING ON ROUTE 128
Location:
  • City of Gloucester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Summer 2029
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $3,300,000.00
    Estimated Total Federal Participating Construction Cost: $3,928,500.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: GLOUCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $3,645,648.00
    State Cost: $911,412.00
    Total Cost: $4,557,060.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/23/2021
    Project Need Form PNF Approved 12/31/1969
    Project Initiation Form PIF Entered 02/23/2021
    Project Initiation Form PIF Approved 02/23/2021
    Project Initiation Form PRC Submitted 02/24/2021
    Project Review Committee PRC Approved 03/03/2021
    Project Management