Project Description:
GLOUCESTER- RESURFACING ON ROUTE 128
Location:
  • City of Gloucester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Koby J Lemrise
    Estimated Total Federal Participating Construction Cost: N/A
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: GLOUCESTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $3,519,936.00
    State Cost: $879,984.00
    Total Cost: $4,399,920.00